Recent Projects
IQS is proud to have provided services for these companies and more:
DE BEERS MARINE
IQS is the contracted 3rd party Inspectorate for all DBM in-port maintenance and capital expenditure projects.
2019
Project QA/QC carried out by IQS, representing the DBM Project Owners Team.
QA/QC, NDT and commissioning activities, undertaken in Gauteng and Western Cape.
MV Coral Sea Offshore Diamond Vessel
Project Duration: Start January 2019 complete October 2019 (10 mths)
MV Mafuta Offshore Diamond Vessel
Project Duration: Start March 2019 complete June 2019 (4 mths)
2018
QA/QC, NDT and commissioning activities, undertaken in Gauteng, Western Cape and internationally, typically Germany, Italy, Poland, Norway, China.
MV Grand Banks Offshore Diamond Vessel
Project Duration: Start January 2018 complete June 2018 (6 mths)
MV Debmar Atlantic Capital Upgrade Project Offshore Diamond Mining Vessel
Project Duration: Start January 2018 complete October 2018 (9 mths)
2017
Coral Sea Diamond Mining Vessel Maintenance In-Port
Project Duration: 4 Months Start January 2017
2016
ARDC PROJECT SS SAM NUJOMA Offshore Diamond Mining Sampling Vessel
Project Duration: Start June 2015 complete December 2016 (18 mths)
MV Debmar Pacific Maintenance Project Offshore Diamond Mining Sampling Vessel
Project Duration: Start July 2016 complete August 2016 (2 mths)
MV Gariep Diamond Mining Vessel Capital Upgrade & Maintenance In-Port
Project Duration: 8 Months Start November 2017
MV Mafuta Capital Upgrade Project Offshore Diamond Mining Sampling Vessel
Project Duration: Start January 2016 complete June 2016 (6 mths)
LESEDI NUCLEAR SERVICES
Ankerlig Power Station
Project Duration: Start Oct 2018 ongoing estimate completion May 2020
Medupi Power Station-Balance of Plant
Project Duration: Start Feb 2013 ongoing estimate completion 2019 (60 mths)
Kusili Power Station-Balance of Plant
Project Duration: Start May 2014 ongoing estimate completion 2019 (52 mths)
ANGLO AMERICAN
VENETIA UNDERGROUND MINING PROJECT Shaft Sinking and Decline shaft development
Project Duration: Start July 2013 complete April 2016
FIRESTONE DIAMONDS LIQHOBONG DIAMOND MINING PROJECT Process and Treatment Plant
Project Duration: Start June 2014 complete December 2016
ADP Projects FLUOROSPAR Process Plant, manufactured and pre-assembled in SA prior to shipment to Canada for installation and commissioning
Project Duration: Start April 2016 complete December 2016