Recent Projects



IQS is proud to have provided services for these companies and more:

DE BEERS MARINE

IQS is the contracted 3rd party Inspectorate for all DBM in-port maintenance and capital expenditure projects.

2019

Project QA/QC carried out by IQS, representing the DBM Project Owners Team.

QA/QC, NDT and commissioning activities, undertaken in Gauteng and Western Cape.

MV Coral Sea Offshore Diamond Vessel

Project Duration: Start January 2019 complete October 2019 (10 mths)










MV Mafuta Offshore Diamond Vessel

Project Duration: Start March 2019 complete June 2019 (4 mths)

2018

QA/QC, NDT and commissioning activities, undertaken in Gauteng, Western Cape and internationally, typically Germany, Italy, Poland, Norway, China.

MV Grand Banks Offshore Diamond Vessel

Project Duration: Start January 2018 complete June 2018 (6 mths)




MV Debmar Atlantic Capital Upgrade Project Offshore Diamond Mining Vessel

Project Duration: Start January 2018 complete October 2018 (9 mths)



2017

Coral Sea Diamond Mining Vessel Maintenance In-Port

Project Duration: 4 Months Start January 2017



2016

ARDC PROJECT SS SAM NUJOMA Offshore Diamond Mining Sampling Vessel

Project Duration: Start June 2015 complete December 2016 (18 mths)



MV Debmar Pacific Maintenance Project Offshore Diamond Mining Sampling Vessel

Project Duration: Start July 2016 complete August 2016 (2 mths)




MV Gariep Diamond Mining Vessel Capital Upgrade & Maintenance In-Port

Project Duration: 8 Months Start November 2017




MV Mafuta Capital Upgrade Project Offshore Diamond Mining Sampling Vessel

Project Duration: Start January 2016 complete June 2016 (6 mths)



LESEDI NUCLEAR SERVICES

Ankerlig Power Station

Project Duration: Start Oct 2018 ongoing estimate completion May 2020

Medupi Power Station-Balance of Plant

Project Duration: Start Feb 2013 ongoing estimate completion 2019 (60 mths)

Kusili Power Station-Balance of Plant

Project Duration: Start May 2014 ongoing estimate completion 2019 (52 mths)

ANGLO AMERICAN

VENETIA UNDERGROUND MINING PROJECT Shaft Sinking and Decline shaft development

Project Duration: Start July 2013 complete April 2016

FIRESTONE DIAMONDS LIQHOBONG DIAMOND MINING PROJECT Process and Treatment Plant

Project Duration: Start June 2014 complete December 2016

ADP Projects FLUOROSPAR Process Plant, manufactured and pre-assembled in SA prior to shipment to Canada for installation and commissioning

Project Duration: Start April 2016 complete December 2016